TIMETABLE FOR COMPLETION - ATTACHMENT U
Chatham University will comply with the following timetable for completion of the remedial measures set forth in the Settlement Agreement and Attachments A - T.
First Year - December 2008 - December 31, 2009
• Provide accessible parking and an accessible path of travel to the academic complex from the Eddy Theater portion of the Library lot, with a ramp and sidewalk system to allow access to the main academic quad level
• Install an accessible entrance to the Braun-Falk-Coolidge academic complex by providing access through Falk Hall at both the new quad and the old quad sides of the complex.
• Eddy Theater
• Item 15 of Attachment T - Access Ramp at Eddy Theater
• Item 1 of Attachment T - Berry Hall
• Item 2 of Attachment T - Access to campus from public transportation
• Item 4 of Attachment T - Pedestrian curb ramp at Woodland Road and Fifth Avenue
• Item 17 of Attachment T - Route to Lindsay House
• Item 19 of Attachment T - New Walkway from Chapel Hill Road to the Boardroom
Second Year - no later than December 31, 2010
• All remaining remedies for the Braun-Falk-Coolidge complex.
• Buhl Science Center
• Dilworth Hall
• James Laughlin Music Center
• Chapel
• Anderson Snack Bar
• Item 3 of Attachment T - Parking and Accessible Route to Playing Fields from Art and Design Center (Old Gym)
• Item 5 of Attachment T - Chapel Hill Road Plaza
• Item 6 of Attachment T - Chapel Hill Road & Old Quad Area
• Item 7 of Attachment T - Walkway from the Chapel Parking lot and Chapel to front of Laughlin Hall
• Item 8 of Attachment T - Walkway from Chapel Hill Road to Coolidge Hall entrance
• Item 9 of Attachment T - Walkway from Coolidge Hall toward Falk Hall
• Item 10 of Attachment T - Walkway from Falk Hall to Braun Hall
• Item 11 of Attachment T - Parking Lot West of Coolidge
• Item 12 of Attachment T - Coolidge Hall Walkway on West Side
Third Year - no later than December 31, 2011
• Jennie King Mellon Library
• Woodland Hall
• Berry Hall
• Lindsay House
• Item 13 of Attachment T - Walkway from Coolidge Hall toward Library
• Item 14 of Attachment T - Walkway between Braun Hall and Woodland Hall
Fourth Year - no later than December 31, 2012
• Mellon Center
• Anderson Dining Hall
• Beatty House
• Item 18 of Attachment T - Walkway from Carriage House to Mellon Center
Fifth Year - no later than December 31, 2013
• Athletic Fitness Center (New Gym)
• Old Gym
• Carriage House
• Item 16 of Attachment T - Walkway from New Quad to Dilworth & Carriage House